General Contractor: Coakley-Williams
Architect: GCM Architects
The Oliver
Robert A. Aird, Inc. installed a continuous fluid-applied air and weather barrier system over exterior sheathing substrates as part of the building enclosure assembly. The system included one coat application over DensGlass Gold® sheathing. Where alternate substrates such as OSB were present, additional coating thickness or secondary applications were coordinated to meet manufacturer performance requirements.
The EIFS assembly incorporated 2.5-inch Owens Corning FOAMULAR® CI-C continuous insulation, adhesively attached using vertical ribbons of Sto TurboStick® to maintain drainage pathways and substrate tolerance. Architectural reveals were installed in accordance with project drawings to achieve the intended façade articulation.
A reinforced base coat assembly consisting of Sto BTS Xtra with embedded 4 oz fiberglass mesh was applied throughout the EIFS areas to provide crack resistance and impact durability. The system was completed with a StoLit® Lotusan® finish in medium texture and single color, offering enhanced hydrophobic performance, color longevity, and reduced surface soiling.
This coordinated enclosure approach ensured thermal continuity, moisture control, and long-term façade performance while delivering the architectural design intent.